Home >
About Us > News >
EHS Building
Subcommittee
EHS Building Subcommittee Update
A STATUS REPORT ON THE PROPOSED NEW HIGH SCHOOL FOR THE COOPERATIVE
SCHOOL DISTRICT
By Warren Henderson, Chairman
Building Committee
Since the Building Subcommittee was formed in late October we have
met five times, made two public briefings to the Cooperative School
Board and held one open forum to hear questions and comments from the
community. A second forum is scheduled for Thursday December 19th at
7:00pm in the High School Annex (old Jr. High) cafeteria (note location
change, not in Science Lecture Hall). In addition, as Committee Chair I
have met many times with representatives of the architects, the
administration and others working to produce the best recommendation for
a new high school. Also, we have established an email address
(newhsproposal@sau16.org)
to provide another way for people to express their views on this
important project. Every email received at this address has been printed
and distributed to the Building Committee and the administration for
their information and consideration.
Our goal in this process is straightforward. We have the opportunity
to build a new high school on a large site in an advantageous location.
We need a solid plan to present to voters in March so that they may make
an informed decision as to whether to rebuild on the existing site or
build new. Voters, then, will weigh both options and make their choice.
School construction to either rebuild or replace a much needed facility
will then begin on one site or another.
This report is intended to be another aspect of our effort to keep
the public informed and involved in the planning process for this
proposed school. When parts of this report rely on information which is
tentative or findings which are preliminary, I will try to so indicate.
My intention is to address as many of the questions posed to the School
Board and/or the Building Committee as possible.
The main components of this status report may be broken down as
follows:
- The building (size, design, elements, athletics)
- The site (size, conditions, environmental impacts)
- The location (transportation, traffic)
- The cost (estimated total cost, comparatives)
- Other (always a favorite!)
THE BUILDING
Preliminary plans show a new building of about 330,000 square feet
capable of housing 1800-2000 students (sufficient to meet the latest 10
year population projections) which is two-story throughout the classroom
wings and much of the core facility and one-story in those sections
which require extra height (auditorium, gymnasium, library) and the
space which surrounds them. The school is all in one building rather
than two or more separate structures.
The design of the new school is based on “flexibility”. Because
educational philosophy and strategy changes, each of the eight classroom
wings (four on each floor) can be organized by grade, by discipline or
to accomplish other objectives. Each classroom wing is subdivided by a
central hallway and can house 450-500 students in classrooms which
average 900 square feet. Each half of each classroom wing begins with a
science classroom/lab (16 in all).
In addition, as expected, the building includes appropriate spaces
for music and art, computers/technology, special education, physical
education, and other essential educational elements. These spaces will
be detailed on a building layout which will be made available once
finalized. As of this date (Dec. 12) this layout is about 98% completed.
While some spaces are still being assigned and reassigned, the building
“footprint” has been finalized, which permits us to determine a reliable
approximate cost.
The building also includes a full gymnasium which can seat 2000, an
auditorium which can seat up to 1000, a cafeteria designed to
accommodate students in only two or three lunch periods rather than
stretching throughout the day, and a substantial library resource. The
building also allocates space for normal school needs such as
administration, guidance, nursing, maintenance, etc.
The building is designed and located on the site in a manner so as to
be efficient in design and materials while giving students and staff a
sense of light and space. Lockers don't line hallway walls (a chief
cause of hallway crowding and chaos). Lockers are organized in groups
outside each classroom wing. The building is located to bring morning
sun into classrooms, entrances and common space. Areas such as the
cafeteria are designed to be useful as space for groups of classes to
gather or for special projects during non-lunch periods, thus increasing
the efficient use of space. While there are an appropriate number of
building exits, access to the building can be carefully controlled for
security purposes. There is much more than can be said here about the
building design. Each of the presentations which the School Board is
offering to interested groups starting in January will feature a
detailed plan of the school building and site.
Before leaving this topic it is important to note that the site is
large enough to provide tremendous improvements in the number, location
and quality of athletic fields. The new site will house a new fully
equipped football stadium with a field that is surrounded by a track and
related track-and-field facilities. In addition, four soccer/field
hockey/lacrosse fields will be located together and a baseball field
plus a smaller softball field will be located in the lower western
corner of the site. In addition there will be outdoor basketball and
tennis courts. All of these facilities will have full and convenient use
of the 1000 parking spaces at the site.
THE SITE
The proposed new school sits on a 118-acre tract of land located in
the northwestern part of Exeter just off what was formerly Route 101 and
is now known as Route 27. The site is bordered on one side by Old Town
Farm Road. The land is farmland, used most recently for a horse farm.
Beginning last summer, soon after the School Board took an option on
the property, professional analysis of the property was begun. Most of
this work has been coordinated by Appledore Engineering, a
Portsmouth-based civil engineering firm in business since the 1980's and
home to 40 skilled professionals with just the kinds of diverse
expertise this project needed.
The main questions about the school site posed to Appledore
Engineering are:
- Is there enough “uplands” (non-wetlands) to locate the school,
parking, athletic fields and access roads?
- Is there hazardous waste, ledge, or other impediments to
construction?
- Is the soil of sufficient quality to provide a safe and stable
building platform?
- Can the site support septic fields and/or a packet wastewater
treatment plant of sufficient size to serve the facility, and will
sufficient water be available to provide for the water needs of the
school?
- Are there wetlands? If so (there are always wetlands!) how much
and where on the site?
- How much wetlands will likely be disturbed by the project?
The responses are as follows:
- Yes, there is enough upland to build the school. About 2/3 of the
site is uplands and nearly all of it is connected (rather than having
remote upland parts of the site that you need but can't get to without
disturbing wetlands). This is illustrated on the site map presented to
the School Board at their Tuesday December 10th meeting.
- No, there is no hazardous waste on the site that has been
identified to date. There has been a complete walk of the property and
relevant state and local records have been reviewed for clues about
possible contaminants. About the worst thing found on the site is a
lot of horse manure, something that you'd expect to find on a horse
farm. That manure will have to be removed, however, before the project
can be completed. Ledge was found only in two areas of the site toward
one corner, far from where the building is planned.
- Yes, the quality of the soils on the property will sustain this
project. 10 test pits were dug in areas throughout the site, and 6
borings have been dug in the area where the building and parking is
planned (more borings are planned) to determine soil quality, ground
water and water table, ledge, etc.
- The preliminary findings reported by Appledore Engineering confirm
that the site can easily sustain septic fields to treat the waste
generated by the school or a wastewater treatment plant. “Perc”
(percolation) soil tests confirmed this. Present plans are to site
septic fields in one corner of the site between two sports fields.
At present, access to sufficient water can only be estimated. Once
a test well is dug, we will have more definitive information.
Permitting for that well is underway. In the meantime, Appledore
Engineering has consulted with RE Prescott Pump Company, one of the
most experienced firms of its type in this region, for their estimate
of water availability based on their work in the area and relevant
expertise. RE Prescott Pump believes that sufficient water will be
available for the school by digging wells on the western part of the
site (the opposite side from Old Town Farm Road).
One factor in that finding is that schools are not particularly
large water users, at least for a building of this size. The school
needs about 12,000 gallons of water per day to keep on site water
tanks full. By comparison, one rule of thumb to estimate residential
water use is 150 gallons of water per day per bedroom. What that means
is that if only 30 3-bedroom houses (both conservative estimates) were
built on this site, those houses would need 13,500 gallons of water,
more than the school is projected to need. In addition, school water
use is much lower during summer months because school is not in
session.
The building committee acknowledges that more definitive findings
are needed in this area and have conveyed this to our professional
consultants.
- Yes, there are wetlands on the site. Thankfully, the two
main areas of wetland are on the southern and western borders of the
property, leaving the center area free for building, parking and
fields.
- About 3.5 acres of wetland will likely be disturbed by the school
project. While we would prefer for the amount to be zero, impact of
this amount for a project this size should not keep the school from
going forward so long as proper care is taken with permitting and
construction.
THE LOCATION
The site for the proposed new high school is located off of Exit 9 of
Route 101. From that exit traffic would travel west about .8 miles down
Route 27 (old Route 101) to the intersection of Route 27 and Old Town
Farm Road. From this point it is about ½ mile to the school site.
Not surprisingly, families who live on that part of Old Town Farm
Road don't much like the idea of all the school traffic coming up their
road. I wouldn't like it if it was me, either. That's one reason the
Building Committee has worked since its formation to obtain “alternate
primary access” to the site directly off Route 27. Simply put, we'd like
to be able to either buy an easement or a small piece of property so we
could build a short road from Route 27 to the school site and not go up
Old Town Farm Road for anything other than secondary or emergency
access. In fact, there's money in the cost estimate for that. However,
we cannot guarantee that we can obtain alternate access. All of the land
which could provide that access is privately owned, and no landowner may
be willing to sell either property or easement. We will continue to make
every effort to address this issue responsibly. As a last resort, we
would use that ½ mile of Old Town Farm Road to provide access to the
site and address related road improvement issues.
Whether the high school stays or moves, it generates a lot of
traffic. Mostly car traffic and some bus traffic. We can make only a
broad estimate of how moving the high school would impact the area it
would leave and the area where it would be located. Some elements of
that estimate are as follows:
Currently, about 100 students walk on average, a number unlikely to
grow even as the school population grows because the area around the
existing site is “built out”.
Roughly 500 students take the bus and about 1000 ride or drive (the
remainder are the walkers).
As school population increases, there is no reliable way to determine
what portion will bus vs. ride or drive, no matter where the school is
located. However, it is safe to assume that the number of students who
walk will drop to virtually zero. With regard to bus transportation, as
student population increases, it is estimated that the same number of
buses will be required with either plan. At the new site, added buses
might be needed to provide for students who now walk. However, more
buses might be needed at the current site as existing parking problems
may cause fewer students to drive.
How would this change in traffic affect the two sites? Some
reasonable conclusions would be:
At the site of the new school, traffic would substantially increase.
On a positive note, this area of town is not densely populated and the
area roads are lightly traveled. In addition, the roads on which most
students would approach the school have substantial capacity. It is
reasonable to assume that most cars driving to the school will use Route
101 and use either Exit 9 eastbound or Exit 9 westbound to approach the
school. Obviously, Route 101 has the capacity to handle this traffic.
Traffic approaching the school from Route 101 will travel about .8 mile
on Route 27. It's worth noting that, until about four years ago, what we
now know as Route 27 in that area was Route 101, the most heavily
traveled east-west roadway in the State of New Hampshire. This road has
handled traffic loads far in excess of what the school would place upon
it.
The only significant traffic issue at the new school site is the last
½ mile which either would travel along a newly constructed road built to
serve the school or along Old Town Farm Road. The Building Committee
prefers the former, as is discussed above. Traffic flow would be
heaviest during the hour before school begins and the hour at which it
ends. It is not possible to accurately gauge likely traffic volume and
we have no comparative measure. We know how many parking spaces there
are at the existing school but we don't know how many additional cars
park off site or how many cars drop off students either at the high
school site or on a nearby road. It is reasonable to assume, however,
that the volume of cars will be sufficient to transport the 1100 that
currently drive or ride plus a portion of the 100 who now walk (the
remainder of that group opting for bus transportation).
Parking at the new site would be vastly improved over current
conditions. The site plan calls for 1000 parking spaces at the new
school site, sufficient to meet the needs of faculty, staff, students
and visitors. Buses waiting in line to either pick up or drop off
students would also be entirely on school property, rather than in the
street as is sometimes the case at the present site.
Turning to the traffic impact on the site of the existing school, and
on traffic impacts around Exeter generally, it appears that relocating
the high school would provide significant traffic and parking relief in
the area surrounding the school and, to a lesser extent, on main roads
in and out of town. From conversations with Exeter police and with
school personnel, we conclude that relocating the high school would mean
substantial traffic relief on Front Street, Lincoln Street, Gill Street
and Linden Street. Traffic congestion relief on downtown Exeter roads
would result from changing traffic patterns. It is reasonable to assume
that high school students living in Stratham, Newfields, northern and
eastern Exeter and much of Brentwood would no longer have to drive
through downtown Exeter to get to school. In fact, only Kensington and
East Kingston, the two least populated towns in the co-op, would be more
likely to drive through Exeter to get to the new school site.
In addition, we believe that the problems related to students who
park off-campus and walk through area neighborhoods to access the
existing school site would disappear, as all students who drove could
park on-campus.
THE COST
Cost of the new high school: Our preliminary estimate for the cost of
building the new high school off Route 27 is roughly $49.5 million. As
has been said publicly, this number is likely to rise and/or fall by
several hundred thousand dollars before we get our final figure as the
remaining variables are factored in. That said, we are confident that
this estimate is within 1% or so of the final cost. This cost will
include:
- Land acquisition
- All architectural and engineering work
- Site improvements
- Building the high school
- Building all related parking, athletic fields and other site work
- An allowance for furnishings and equipment (over and above what will
be brought over from the existing site)
- The estimate includes necessary contingency funds in accordance with
standard practices.
- The estimate includes funds to either acquire alternate primary
access to the site and build an access road or to make road improvements
on Old Town Farm Road.
Cost comparison, new high school vs. renovation of existing campus:
To date, Co-op voters have committed:
- $35.5 million in the original vote to renovate the existing school,
plus
- $ 3.5 million subsequently to account for added site costs, plus
- $ 4.3 million last March to separate SST from the main site (the new
high school plan contemplates keeping SST at the existing facility).
That adds up to $43.3 million to renovate the existing high school
and move SST off site vs. $49.5 to build a new school on a bigger site
in a better location. Further, it is worth noting that discussions are
currently underway with the architect and construction manager for the
renovation project to update construction costs, as has been done each
year since the project was originally approved. The total cost may go up
or down again based on those findings, which should be known within the
next week or so.
OTHER
What we now know about the building, site, location, transportation
and cost is incorporated into the report above. This information will be
expanded and finalized as more details are known. Many of the questions
we have received relate to those subjects. However, some additional
questions raised relative to the new high school project:
Q -- “Can't we buy the three houses that sit between the high school
and old junior high, along with the Court Street property owned by the
Exeter School District, and use that extra space to expand the
renovation project?”
A - The three houses located near the high school have a combined
appraised value of $584,000 and have a total acreage of .93 acre (that's
less than one acre). Even if those houses could be acquired for their
appraised value, paying nearly $600,000 for less than one acre doesn’t
make much sense because you pay a lot and gain a little. This doesn’t
include demolition costs. The Court Street property has about 2.8 useful
acres out of a total of 3.8. Even if the land was gifted to the Co-op,
it would cost an estimated $170,000 to demolish the existing building
and improve the site and then it could only be used for parking (with a
mile walk or shuttle service) unless money was spent to rebuild on the
site. In sum, this option would generate less than five acres at a land
cost of almost $800,000, a poor value in our estimation.
Q -- “Can we use the Kensington land recently acquired as a remote
extension of the existing high school site?”
A - Most of the Kensington land is not suitable for substantial
construction. The 18 useful acres on the site were intended to house
sports fields.
Q -- “Could we buy the Tyco properties and relocate the high school
to that site?”
A - The total size at the Tyco property, that being the land and
buildings on both sides of the road, is 52 acres. However, according to
the Realtors who have listed the site, only 13 of those acres are
“upland”, severely limiting the utility of the site as a high school
setting. In addition, the $5.5 million asking price includes corporate
buildings which are well designed for business use but not necessarily
for school use.
Q -- “Won't putting a school on the Route 27 site cause a housing
boom in that area?”
A - Not likely. This concern was based on the impact of extending
municipal water and sewer to the site. Residential lot sizes may be
reduced, and thus density increased, in areas served by water and sewer.
Therefore, the thinking went, there could be a housing boom and the
related adverse tax and infrastructure impacts. However, the current
plan is NOT to extend municipal water and sewer to the site, laying that
concern to rest.
Q -- “What is the plan for the existing high school site if a new
high school is built?”
A - This determination will be made by the School Board, although the
Building Committee intends to offer recommended criteria to govern
future use or sale. A few things we can safely say about the existing
site are:
It will be in use as a high school for the three years it will take
to build a new school. Therefore, any stated intention about the
existing school site would simply be speculation. Even if it was the
will of the voters to sell the existing site, you couldn't really vacate
the property until 2005.
Voters may dictate its use(s) and/or its disposal. In fact, there
will be three annual elections between now and then.
SST will likely stay in its current space because the State of NH
provided 100% of the funding for its construction in 1980 and we have an
obligation to provide at our costs this or its equivalent. Some adjacent
space may be added to it if the high school is relocated. This option
would be preferable to the alternatives identified to date to move SST
off site.
Building Committee recommendations for future use of the existing
site would be made this month or in early January and will be made
public as they are delivered to the School Board.
FINAL COMMENTS
This status report is designed to be just that - a snapshot of a
complex project which people from the towns of SAU 16 are working hard
to complete and present for the consideration of the voters on March 11,
2003. We know that many people have wanted a new school all along. We
know that some will fight the site on Old Town Farm Road no matter what.
We know that most people will wait to hear the facts and weigh their
options before they make a decision.
If this report contains errors, omissions or misstatements, that's my
fault and no one else's. I want to thank everyone who is serving on the
Building Committee for their time, energy and guidance. More information
will be presented as it becomes available. Any group which wishes to
receive a full presentation about the proposed new high school starting
the first week in January is invited to contact School Board member
Donna Bates at 772-9001. Ms. Bates is coordinating these presentations.
We will do our best to present voters with the best option we can
conceive. A safe and happy holiday to all.
Warren Henderson
Download/View Report in Word Format (.doc)
Download/View Report in Adobe Acrobat (.pdf)
Top
|